Licences and Permits for Your Project
Overview of the Design & Construction Phase
Design and Construction covers the process from project conception to energisation. In general, this stage can be broken down in to 5 phases.
For certain licences, whether you need them depends on your project's scope. These are marked as project specific in the results below. All other licences are mandatory, meaning they are required for your project.
Design and Construction Steps
01 STEP
Design
Complete technical designs, environmental studies and your project plan.
02 STEP
Planning
Identify and submit an application to the relevant planning authority.
03 STEP
Grid Connection
Get the appropriate grid connection offer for your project.
04 STEP
Pre-construction
Prepare to construct and decide how you'll sell your electricity (route to market).
05 STEP
Construction
The construction of your renewable energy project and related grid infrastructure.
Use the licence & permit finder
- Answer a few quick questions
- No personal information required
- Get a curated list of licences and permits specific to your project
The content of this website is provided for information purposes only and does not constitute legal or other advice. Any guidance given by the SEAI shall not be considered as advice of the SEAI. You should always consult your own professional advisors (e.g. your solicitor) before making any decisions relating your planned project or committing any expenditure to your planned project. For further details see our Terms of Use.
While we work to keep all information up-to-date, the conditions around specific licences change regularly. Please check the issuing body website for the latest information.